Judge hears arguments in Las Vegas water pipeline fight

A years-long fight over a plan to build a water pipeline along the Nevada-Utah state line to bring groundwater to Las Vegas is about to get a first-ever hearing before a federal judge.

By KEN RITTER

Associated Press

Published on August 1, 2017 9:37AM

This March 2012, file photo shows pipes extending into Lake Mead well above the high water mark near Boulder City, Nevada. A years-long fight over a plan to build a 263-mile water pipeline along the Nevada-Utah state line to bring rural groundwater to Las Vegas is about to get a first-ever hearing before a federal judge in Nevada. The pipeline could cost billions of dollars to build, but the Southern Nevada Water Authority says it may become essential if drought keeps shrinking the Lake Mead reservoir on the Colorado River.

Julie Jacobson/Associated Press

This March 2012, file photo shows pipes extending into Lake Mead well above the high water mark near Boulder City, Nevada. A years-long fight over a plan to build a 263-mile water pipeline along the Nevada-Utah state line to bring rural groundwater to Las Vegas is about to get a first-ever hearing before a federal judge in Nevada. The pipeline could cost billions of dollars to build, but the Southern Nevada Water Authority says it may become essential if drought keeps shrinking the Lake Mead reservoir on the Colorado River.

Buy this photo

LAS VEGAS (AP) — Momentum and mitigation were two issues mentioned Monday by a federal judge who will decide whether environmental studies need to be redone for a massive eastern Nevada water pipeline proposed to draw rural water to serve thirsty Las Vegas tourists and residents.

U.S. District Judge Andrew Gordon showed with his questions to attorneys that he is weighing environmentalists’ warnings that the project would create dustbowls in valleys along the Nevada-Utah state line against Southern Nevada Water Authority assurances that if there wasn’t enough water, the state’s top water official wouldn’t approve the rights to pump.

State Engineer Jason King “can only approve water rights if recharge equals discharge,” authority attorney Hadassah Reimer said when the judge asked if the Spring, Cave, Dry Lake and Delamar valleys could really go dry.

“The authority’s position is it is the state engineer’s responsibility to make sure that doesn’t happen,” Reimer said.

King’s approval for the proposal in March 2012 is being challenged separately, in Nevada state court.

Attorney Simeon Herskovits, representing the Great Basin Water Network, told Gordon that the water underground dates to ice ages and isn’t replenished today. He called environmental damage inevitable.

“The project is designed to take the maximum amount of water from these basins in perpetuity,” he said.

Environmental studies took eight years before the bureau in December 2012 granted permission for the pipeline to cross 263 miles of federal land from sparsely populated White Pine and Lincoln counties to the Las Vegas area, home to 2 million residents and host to 40 million tourists a year.

In response to another question from the judge, government lawyer Luther Hajek said the federal Bureau of Land Management “just issues the right-of-way. It doesn’t have final say on how much water is pumped.”

State and federal go-aheads brought challenges in state and federal courts from environmentalists, activists, local governments in rural towns in the two counties, plus the Duckwater and Ely Shoshone tribes and the Confederated Tribes of the Goshute Reservation in Utah.

No tribe in the area was properly consulted, and none signed off on the plan, Rovianne Leigh, attorney for the Goshutes, said Monday.

She described tribal elders’ fears that a meadow wetland in Spring Valley will go dry. The site is revered and used in sacred ceremonies, and remembered as the site of massacres 150 years ago.

“When the water is gone, it is gone forever,” Leigh said.

Water agency officials concede it will cost billions of dollars to build a pipeline to carry 75,000 gallons of water daily a distance comparable to a drive from Los Angeles to Las Vegas. But they say it may become essential if drought keeps shrinking the Lake Mead reservoir on the Colorado River, which supplies 90 percent of Las Vegas drinking water.

Project planners say that once wells are drilled and water begins flowing, engineers can measure the effects on the environment and correct, or mitigate, any damage that might result.

“Can the (Bureau of Land Management) stop this project before water is drawn?” the judge mused from the bench. “Isn’t this a case of momentum at this point? A ball rolling downhill?”

Gordon, who also has more than three years’ worth of written court filings from all sides, said he expects to issue a written decision within several weeks.

That would be before King holds hearings in late September on a state judge’s order that he reconsider whether there is enough underground water to supply the pipeline.